Copper Mining Process | Operations | Minto Explorations
Since restarting operations in October 2019 we have processed 391,964 dmt of ore through the mill and produced 19,187 dmt of copper/gold concentrate. Mill throughput has increased from 2458 tpod to 3965 tpod. The mill is currently running on a 2 week on/2 week off schedule as we continue to develop Copper Keel and ramp up operations.